Downtown construction update

 This is an update on the progress of the New Downtown Conference Center.

Most of the progress has occurred inside the building, but there are some significant  changes from last month.

The roof is complete with the exception of the Auditorium and Porte-Cochere

Waterproofing and sheathing of the building skin is complete with the exception of the main entrance

Brick veneer has begun on the south and east elevation

The Terrace stairs have been poured down the bottom landing

The EIFS is complete at the Parking Deck and the curbs have been poured for the Church St. Parking Deck entrance.

The operable wall track has been installed and the sound partitions are being covered up with drywall

Drywall cover-up inspections have been received for the south end of the building

The interior wall framing is 90% complete

Ceiling framing in the Ballroom is on-going

Window installation is complete with the exception of the Boardroom and main entrance.

For more information visit the city website at www.ci.douglasville.ga.us